
Only the bottom part of the ingot is used.

ultimate tensile stress and elongation checked. This must be near enough equal in all 3 directions.
After rough machining it is put in for a thermal stability test. For this final machining is given to the areas indicated. The end flange is marked at 90' intervals. Then the rotor is encased in a furnace. Pokers are placed onto the machined areas and accurate micrometer readings taken. The rotor is rotated though 4 positions marked on the flange.
The rotor is then heated to 28'C above normal operating temperature and slowly rotated.
Measurement is then taken at hourly intervals until 3 consistant readings are taken ( hence the rotor has stopped warping). The rotor is then allowed to cool and a set disparity allowed.
For turbine sets operated at greater than 28'C above their designed superheat then run the risk of heavy warping as well as high temperature corrosion and creep.
Final machining is now given. The rotor is statically balanced and then dynamically balanced and check to ensure homogenity.The rotor is bladed then again dynamically balanced.

Most modern HP turbine rotors are of the Rateau or pressure compounded design.
Reduced number of stages ( 8 to 10 ) give a shorter rotor and provides savings in weight and length. Also provides for better critical vibration characteristics.
After forging the rotor is machined, wheels may be parallel or slightly thickened at the base . The methods is also used for the LP turbine which has 7 to 9 stages plus 2 to 3 astern.
After rough machining rotor is given a thermal stability test, after further machining and fitting of blades the rotor is given a static and dynamic balance.
This design is known as the Gashed disc rotor and gives a minimum shaft thickness and hence a minimum area for gland sealing to prevent steam leakage.
e